NEC 705.12(B)(2) · 240.6(A)

Can My Panel Handle Solar?

The question is really how big a solar backfeed breaker your busbar can take. The NEC 705.12 120% rule answers it: 120% of the busbar ampacity, minus the main breaker, rounded down to a standard breaker. Here is that threshold by busbar and main size, worked, plus the panels that need a line-side connection instead.

Quick answer: On a 200A busbar with a 200A main, the 120% rule allows 120% × 200 = 240A total, less the 200A main = 40A of room, which is a standard 40A backfeed breaker (NEC 240.6(A)) supporting about a 32A / 7.7 kW continuous inverter. A smaller main leaves more room; a 225A “solar-ready” bus with a 200A main takes a 70A breaker. Round down to a standard size, never up.

Max solar backfeed breaker, by busbar and main

Find your panel's busbar rating down the left and your main breaker across the top. The cell is the largest standard backfeed breaker the 120% rule allows, with the continuous inverter output it supports (breaker ÷ 1.25) below it.

Maximum standard solar backfeed breaker (NEC 705.12(B)(2), rounded down per 240.6(A)), with supportable inverter continuous output. “n/a” = a main cannot exceed its busbar.
Busbar100A main125A main150A main200A main
100A bus20 A16 A invertern/an/an/a
125A bus50 A40 A inverter25 A20 A invertern/an/a
150A bus80 A64 A inverter50 A40 A inverter30 A24 A invertern/a
200A bus125 A100 A inverter110 A88 A inverter90 A72 A inverter40 A32 A inverter
225A bus150 A120 A inverter125 A100 A inverter110 A88 A inverter70 A56 A inverter

Each breaker is 120% of the busbar less the main, rounded DOWN to a standard 240.6(A) size (a raw 140A allowance becomes a 125A breaker, a raw 55A becomes 50A). The inverter figure is the breaker ÷ 1.25, the continuous output the breaker supports. The branch conductors to the inverter are sized separately, at 125% of the inverter output.

Scope: read this before you size anything

This is the opposite-end 120% configuration: a utility main at one end of the busbar and the solar breaker at the far end, with the required “do not relocate” label. Confirm the busbar rating on the panel label (it can differ from the main or the panel's marketing rating) and the opposite-end placement before you size anything.

The matrix assumes the only two sources on the bus are the utility main and this one solar breaker. If the panel already carries any other backfed source – a battery inverter, a second PV array, a generator interlock – you must subtract 125% of each of those too, because the 120% allowance covers the main plus every backfeed breaker, not the main alone. And the 120% rule applies to every busbar in the backfeed path: if this panel feeds through to a subpanel, that subpanel busbar and the feed-through conductors must pass it too – a downstream busbar can be the real limit.

It does not cover main-lug-only panels (no main to bound the bus, they use the 100% sum rule of 705.12(B) instead), center-fed, or split-bus panels. When no standard breaker fits, the path is a supply-side (line-side) connection per NEC 705.11 ahead of the main, or a listed power control system (NEC 705.13) that caps bus current – either can add a larger system without a service upgrade.


The check, worked (NEC 705.12 120% rule)

Take 120% of the busbar ampacity, subtract the main breaker rating, and round the result down to a standard breaker. A 200A busbar: 120% × 200 = 240A allowed on the bus. Subtract a 200A main and 40A is left, which is already a standard 40A breaker. That breaker supports an inverter up to 40 ÷ 1.25 = 32A continuous, about 7.7 kW at 240V. If instead the main were a derated 150A, the room grows to a 90A breaker. Every number on this page is computed by the same locked engine the load calculator runs, verified against NEC 705.12 and Table 240.6(A) on every deploy.

New: run this inside your AI assistant

Prefer to just ask? Add this to Claude, free.

Connect Intry to Claude once, then just say “use Intry to…” to run the solar backfeed breaker calculator from a plain-English question, on your phone, on the job. You get the number, the verdict, and the cited NEC section, computed live, not guessed. Works on every Claude plan.

Use this in Claude

Frequently Asked Questions

Can my 200A panel handle solar?

Almost always. By the NEC 705.12(B)(2) 120% rule, a 200A busbar allows 120% x 200 = 240A of total supply. Subtract a 200A main and 40A of room is left for a backfed solar breaker, which rounds down to a standard 40A breaker (NEC 240.6(A)). That supports a 32A continuous inverter output, roughly 7.7 kW at 240V, which covers a typical residential system. If your main is smaller than the busbar (a derated or subpanel main), the room grows: a 200A bus with a 150A main leaves room for a 90A breaker. This assumes nothing else is already backfeeding the bus: if the panel already has a PV or battery breaker, subtract 125% of that too, since the 120% allowance covers the main plus every backfed source.

What is the 120% rule for solar?

It is NEC 705.12(B)(2). Where the utility main and a backfed solar breaker sit at OPPOSITE ends of a busbar that carries loads, the sum of 125% of the source output current and the busbar's overcurrent device (the main) must not exceed 120% of the busbar ampacity. In practice, because the backfed breaker is already sized at 125% of the inverter's continuous output, installers apply it as: max solar breaker = (120% x busbar) minus the main, rounded down to a standard breaker size. The extra 20% headroom is the buffer that keeps the bus from overheating when both sources push current at once.

Why do I round the backfeed breaker down and not up?

Because the 120% figure is a ceiling on the total, not a breaker size. A 200A bus with a 200A main leaves 40A of room, and 40A happens to be a standard breaker. But a 200A bus with a 100A main leaves 140A of room, and 140A is not a standard breaker, so it rounds DOWN to 125A per NEC 240.6(A). Rounding up would exceed the 120% ceiling and overload the bus. Rounding down is the conservative, universally taught practice: the breaker is always at or below the room the code allows.

What if no breaker fits, or my panel is main-lug-only?

Then the load-side (120%) method is not your path, and that is a real answer, not a failure. If the main already uses the full 120% allowance, or the panel is main-lug-only (no main breaker to bound the busbar), you have two routes: a supply-side (line-side) connection per NEC 705.11, tapping ahead of the main, or a listed power control system (NEC 705.13) that actively limits bus current and can fit a larger PV-plus-battery system without a service upgrade. A main-lug-only panel actually uses the 100% sum rule (705.12(B)), not the 120% rule. Center-fed and split-bus panels are also excluded from the simple 120% form. This tool covers the standard opposite-end 120% configuration.

Does the backfeed breaker size equal my inverter size?

No, and mixing them up is the common mistake. The matrix gives the max BACKFEED BREAKER. The inverter's continuous output current is the breaker divided by 1.25 (the breaker is 125% of the continuous output). So a 40A backfeed breaker supports up to a 32A continuous inverter, about 7.7 kW at 240V. Size the breaker from this rule; size the inverter (or the number of microinverters) to stay at or under the breaker's supported current.


Related Calculators